Dear All
Multiple PR s with same material, delivery date, price, plant etc with same source of supply were generated out of MRP.
Converted these to PO s using ME59N by selecting the " Generate Schedule Lines " option in the Other Parameters section so that all these PR s will be converted to one line of PO and quantity added up to one item.
This worked and one PO created.
But when checked MD04 the same PO and item is shown as many times as no of PR s converted.
Is it possible to display it as One PO item itself in MD04?
Please let me know your views